Question calculate the bcwp bcws cpi spi cv and sv for the


The project started and your immediate supervisor asked for a field report on day 10. The field report you submitted on day 10 is given below.

Field Report at Day 10

Activity

Actual Completion %

Cost Incurred

A

100

2400

B

100

1200

C

100

4000

D

80

4000

E

25

4000

F

0

0

Question: Calculate the BCWP, BCWS, CPI, SPI, CV, and SV for the field report day 10. Show your calculations, and summarize the results on a table.

Solution Preview :

Prepared by a verified Expert
Business Management: Question calculate the bcwp bcws cpi spi cv and sv for the
Reference No:- TGS01668473

Now Priced at $20 (50% Discount)

Recommended (91%)

Rated (4.3/5)