Quantitative analysis-pert


Quantitative analysis: PERT

A project having the following six activities:

Activity    Immediate Crash
Predecessors    Time (weeks)    Max Crash cost per week
A    none    7    7    N/A
B    none    3    2    $750
C    A    5    3    $1,000
D    A, B    6    4    $2,000
E    C, D    4    3    $1,250
F    D    3    2    $1,000

1. Draw the project network and list the earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF) for each task

2. List the tasks on the critical path

3. What is the expected project duration in weeks?

4. What is the slack for each activity?

A: ________ B:_______ C:________    D:_______ E:_______ F:_______