Quantitative analysis-crashing problem


Assignment:

Q1. Development of a new deluxe version of a particular software product is being considered.  The activities necessary for the completion of this are listed in the table below.

Activity

Normal Time

Crash Time

Normal Cost

Crash Cost

Immediate

Predecessor

A

4

3

2000

2600

-

B

2

1

2200

2800

-

C

3

3

500

500

-

D

8

4

2300

2600

A

E

6

3

900

1200

B

F

3

2

3000

4200

C

G

4

2

1400

2000

D,E

Indirect costs = $200/week

Penalty (one time) = $4000 after week 12 (penalty is in effect at week 13)

Bonus (one time) = $2500 at week 10

1) What is the expected completion time for the project (before crashing)?

2) What is the critical path?

3) What activities will you crash?

4) What is the optimal time for the project?

5) What is the total cost of the project after crashing?

Q2. 

Activity     Pred              Normal Time         Normal Cost            Crash Cost/wk      Max Crash

A              --                        4                          7,000                        1,000                      1

B              A                         6                          5,000                        2,500                      2

C              B                         10                       13,400                        3,800                      1

D              C                         12                         9,500                        -------                      0

E               A                         23                       17,700                        3,600                      3

F               E                          4                          4,400                        2,000                      1

Indirect Costs = $2000/wk

Penalty = $1600/wk after week 28

Bonus = $5000 at week 22

1)   What is the expected time of completion for the project?

2)   What is the critical path?

3)   What is the first activity you will crash?

4)   What is the second activity you will crash?

5)   What is the total cost of the project after crashing?

6)   What is the optimal time of completion for the project?

Q3. A different version of the software product (from last week's problems) is also being considered.  The activities necessary for the completion of this are listed in the table below.

Activity

Normal Time

Crash Time

Normal Cost

Crash Cost/wk

Immediate

Predecessor

 

 

 

 

 

 

A

4

3

2,000

400

-

B

5

3

2,200

300

A

C

3

3

500

-----

-

D

8

4

2,400

50

A

E

6

3

900

150

B

F

3

2

3,000

600

C

G

4

2

1,700

700

D,E

Indirect costs = $450/week

Penalty = $100/week after week 12 (penalty is in effect at week 13)

Bonus (one time) = $2500 at week 8

(a) What is the expected completion time for the project?

(b)  What is the critical path?

(c)  What is the critical path after crashing?

(d) What is the optimal time for the project?

(e)  What is the total cost of the project after crashing?

Provide complete and step by step solution for the question and show calculations and use formulas.

Solution Preview :

Prepared by a verified Expert
Mathematics: Quantitative analysis-crashing problem
Reference No:- TGS01919886

Now Priced at $20 (50% Discount)

Recommended (94%)

Rated (4.6/5)