Q1 from the critical chain perspective it is generally


Q1. From the Critical Chain perspective, it is generally better to schedule work:
a. Concurrently
b. Sequentially
c. in a staggered fashion
d. so that critical tasks can be crashed early

Q2. A man's weight represents what kind of measure?
a. interval scale data
b. ordinal scale data
c. nominal scale date

d. precise measure

Q3. Critical chain rejects the value of the traditional precedence diagram method.
a. true
b. false

Q4. The resource planning tool that enables us to identify who we need to carry out what tasks is called:
a. a resource Gantt chart
b. a resource ogive
c. a resource matrix ( also called responsibility chart)
d. a resource loading chart (also called a resource histogram)

Q5. If BCWP=$500, BCWS=$600, ACWP=$400 and EAC=$900, schedule variance is:
a. -$100
b. $100
c. -$200
d. $200

Q6. An advantage of the product-oriented WBS is that it:
a. provides an excellent view of the whole product
b. focuses on the schedule of the project
c. focuses on the cost of the project
d. is logical, and fairly easy to read

Q7. If BCWP=$500, BCWS=$600, ACWP=$400 and EAC=$900, the schedule performance index (SPI) is:
a. 1.33
b. 0.83
c. 0.80
d. 1.20

Q8. Buffers are used to address the problem of:
a. Law of diminishing returns
b. Parkinson's Law
c. The Peter Principle
d. Complexity Law

Q9. A key role of a project manager in time-boxed scheduling is to:
a. prepare and present the features of the final deliverable to the project team
b. teach team members how to use scheduling software
c. develop the WBS

d. facilitate the project team's prioritization meetings

Q10. Cost estimates:
a. must be accurate to within +/- 5%
b. distribute project funds according to time lines
c. are prepared after the budget has been determined
d. are prepared before the project budget

Q11. According to the TOC, multitasking often results in:
a. increased quality
b. increased efficiency
c. decreased requirements for resources
d. decreased accountability

Q12. A new product faces two pay-off possibilities. It will either make $100 or $120. The probability of making $100 is 0.4, while the probability of making $120 is 0.6. Conduct a Monte Carlo simulation to simulate the new product's pay-off, using the following random numbers to compute your answer: 83, 28, 82, 36, 91, 9.
a. $110
b. $112
c. $114
d. $115

Q13. The Theory of Constraints (TOC) was originally developed:
a. by the Navy
b. by Du Pont
c. for the service sector
d. for manufacturing

Q14. The WBS is useful when:
a. conducting a top-down estimate
b. conducting a parametric cost estimate
c. conducting a bottom-up estimate
d. allocating human resources to tasks

Q15. The only time to conduct effective estimation in project management is during pre-project (initiation) phase.
a. true
b. false

Q16. The most valuable tool for tracking schedule performance is:
a. the PERT/CPM network diagram
b. milestone charts
c. S-curves
d. Gantt charts

Q17. A basic premise of time-boxed scheduling is that:
a. perfection is the ultimate goal of scheduling
b. heavy use of scheduling software ensures project success
c. 'You can't have it all'
d. it is wrong to scale back on technical features during scheduling, since this reduces the quality of the deliverable

Q18. The critical chain approach ties schedules to resource availability.
a. true
b. false

Q19. An important function of risk assessment groups (RAGs) is to:
a. provide guidance to the organization on how to manage risk
b. kill projects that are not going to be successful
c. conduct Monte Carlo simulations on all projects
d. develop project cost estimates

Q20. The internal rate of return is a project selection technique that examines at what point cumulative income more than offsets cumulative investment.
a. true
b. false

Q21. The most accurate way to measure earned value (BCWP) is:
a. employ the 50:50 Rule
b. employ the 0:100 Rule
c. track milestone performance
d. use expert judgment of project team members

Q22. If BCWP=$500, BCWS=$600, ACWP=$400 and EAC=$900, the cost performance index (CPI) is:
a. 1.33
b. 1.00
c. 0.80
d. 1.25

Q23. Project buffers are placed at:
a. the beginning of critical chain activities
b. the end of critical chain activities
c. the beginning of project milestones
d. the end of project milestones

Q24. Which of the following approaches is likely to call for multitasking?
a. fast tracking
b. crashing milestone activities
c. crashing non-critical activities
d. configuration management

Q25. Another name for Gantt chart is precedence diagram.
a. true
b. false

Q26. If you want to shorten the length of a project, you must:
a. spend more money
b. shorten the free float
c. shorten the critical path
d. cut back on the features you plan to deliver

Q27. The bottom level of a WBS is called:
a. work package
b. cost account
c. code of accounts
d. chart of accounts

Q28. Multitasking creates harmony among project tasks.
a. true
b. false

Q29. If BCWP=$500, BCWS=$600, ACWP=$400 and EAC=$900, what is project cost and schedule status?
a. under budget, behind schedule
b. over budget, behind schedule
c. over budget, ahead of schedule
d. under budget, ahead of schedule

Q30. Which of the following can be described as very crude cost estimates?
a. indirect project cost estimation
b. preliminary estimates
c. definitive estimates
d. conceptual estimates

Q31. 'Concrete drying' is an example of:
a. a working time task
b. an elapsed time task
c. a working time and an elapsed time task
d. hard logic

Q32. The parametric estimating technique is typically used in developing definitive estimates.
a. true
b. false

Q33. Definitive estimates are derived from:
a. Top-down estimates
b. Expert judgment cost estimates
c. Bottom-up estimates
d. Order of magnitude estimates

Q34. Both PERT/CPM and the critical chain approaches treat resources as bottlenecks.
a. true
b. false

Q35. 'Earned value' is a measure of:
a. planned cost
b. planned schedule
c. actual cost
d. work performed

Q36. The S-curve:
a. provides information about cumulative expenditures at a given point in time
b. is a resource loading chart
c. is a scheduling tool
d. tracks achievement of milestones

Q37. Typically, feeder buffers are added to resources at:
a. the point where a non-critical chain path joins the critical chain
b. the beginning of the non-critical chain path
c. the beginning of the critical chain path
d. in the middle of non-critical chain path

Q38. If BCWP=$500, BCWS=$600, ACWP=$400 and EAC=$900, cost variance is:
a. -$100
b. $100
c. -$200
d. $200

Q39. In estimation, estimating a current state of affairs is generally easier than estimating a future state.
a. true
b. false

Q40. According to the Critical Chain perspective, when computing task durations you should:
a. estimate the median duration of the tasks
b. add buffers task by task
c. select a duration that has a 90% chance of success
d. make a best estimate, then multiply it by a fudge factor

Q41. A problem with time-boxed scheduling is that it requires solid quantitative skills to be able to use it effectively.
a. true
b. false

Q42. Soft logic means that:
a. task B must follow task A
b. if task B must follow task A, then task C must also follow task B
c. task A and task B are carried out concurrently
d. while task B is depicted as following task A, the dependency relationship is not required

Q43. If an analysis of cost variance for a given month shows we have spent $10, 00 more than we planned, what conclusion can we make?
a. We are experiencing a cost problem
b. We don't have enough information to determine project status for the month
c. We are saving money
d. We are slipping our schedule

Q44. Using either working time or elapsed time to calculate the time it will take to complete a task produces the same results.
a. true
b. false

Q45. Over five quarters, revenue generated by Alpha Enterprises was: 10, 14, 12, 16, 20. Using the exponential smoothing technique, calculate smoothed values for the 2nd, 3rd, 4th, and 5th quarters given that a = 0.5:
a. 12, 13, 14, 18
b. 12, 12, 14, 17
c. 12, 14, 16, 18
d. 12, 14, 16, 20

Q46. Prioritization is the foundation of time-boxed scheduling.
a. true
b. false

Q47. Over five quarters, revenue generated by Alpha Enterprises was: 10, 14, 12, 16, 20. Using moving averages for two-quarter time periods, calculate smoothed values for the 2nd, 3rd, 4th, and 5th quarters:
a. a) 12, 13, 14, 18
b. b) 12, 12, 14, 17
c. c) 12, 14, 16, 18
d. d) 12, 14, 16, 20

Q48. Crashing is used to speed up work and it generally leads to efficient use of resources.
a. true
b. false

Q49. The leading tool for trend extrapolation is:
a. a) Scenario building
b. b) Monte Carlo simulation
c. c) regression analysis
d. d) multidimensional scaling

Q50. Good estimation practice requires that estimates be updated when project tracking efforts indicate that critical path tasks cannot be completed as planned.
a. true
b. false