Q. A software project is planned to cost 95PY in a period of 1 year and 9 months. Calculate the peak manning and average rate of software them build up.

Ans. Software project cost                               K=95PY

Peak development time                        td=1.75years

Peak manning                                      =mo=K/td√e

95/(1.75 *1.648) = 32.94=33persons

Average rate of software team build up

=mo/td=33/1.75=18.8 person/ year or 1.56 person / month.