Provide a project objective associated with the astin


PROJECT QUESTIONS & TASKS

1. Provide a project objective associated with the Astin Martin Graphics project. Include a list of assumptions about the project.

2. What is a work breakdown structure? What is a responsibility matrix? Using the Astin Martin project activity list and activity duration schedule, create a WBS and RAM. Work Breakdown Structure ??? Responsibility Assignment Matrix

3. Create a network diagram (graphical diagram) that shows the sequence and dependent relationships identified in the Astin Martin project activity list and activity duration schedule.

4. Using the project start time and the required completion date and the project activity list and activity duration schedule, calculate the ES, EF, LS, and LF times and total slack for each activity. Show results in table form.

If your calculations result in a project schedule with negative total slack, revise the project scope, activity estimated durations, and/or sequence or dependent relationships among activities to arrive at an acceptable baseline schedule for completing the project within the required time line. Describe (including tables) the revisions you made.

5. List all activity costs. From the project activity list and activity duration schedule, estimate the cost of each activity. Then, determine the Total Budgeted Cost (TBD) for the Astin Martin Graphics project. Provide the information in table format by month.

6. Provide a cumulative budgeted cost curve for the Astin Martin Graphics project. Provide in appropriate graph format.

7. Astin Martin Graphics wants to know if you plan to use a management reserve for their project. Explain what the term reserve means and why you will use contingency reserve in the project or not.

8. Astin Martin Graphics wants to know how JBB Software plans to employ cost management and earned value (EV) in their project. Define to them the following: TBC, CBC, CAC, CEV CPI, CV, FCAC, TCPI. In addition, explain to Astin Martin Graphics why it is necessary to calculate the earned value of work performed and how it is done.

9. Astin Martin Graphics is concerned about how JBB Software will manage risks. Describe what JBB Software plans to do in order to manage risk on the Astin Martin Graphics project and if a risk assessment matrix will be employed and why.

Attachment:- Project Management.rar

Solution Preview :

Prepared by a verified Expert
Operation Management: Provide a project objective associated with the astin
Reference No:- TGS02546746

Now Priced at $70 (50% Discount)

Recommended (94%)

Rated (4.6/5)