Prototyping differs from the traditional systems


1. Prototyping differs from the traditional systems development lifecycle, in that end-users

a. have no input

b. contribute heavily throughout development

c. contribute only during testing.

d. are important only during the conversion phase.

2. A PERT chart

a. shows each task as a horizontal bar without identifying the sequence of tasks

b. shows a project as a network diagram identifying the sequence of tasks

c. is the same as a system portfolio

d. is shown as a waterfall.