Projected direct materials cost


Armstrong, Inc. uses a flexible budget. Armstrong produced 16,100 units in May incurring direct materials cost of $20,769. Its master budget for the year projected direct materials cost of $366,660, at a production volume of 291,000 units. A flexible budget for May should reflect direct materials cost?