Project to be scheduled using cpm


Problem: The following activities are part of a project to be scheduled using CPM:

Activity Intermediate Predecessor Time (WEEKS)
A 6
B A 3
C A 7
D C 2
E B,D 4
F D 3
G E,F 7

a. Draw the network.

b. What is the critical path?

c. How many weeks will lit take to complete be project?

d. How much slack does the activity B has?

Solution Preview :

Prepared by a verified Expert
Project Management: Project to be scheduled using cpm
Reference No:- TGS01953411

Now Priced at $20 (50% Discount)

Recommended (99%)

Rated (4.3/5)