Project s costs 11000 and its expected cash flows would be


Capital budgeting criteria: mutually exclusive projects

Project S costs $11,000 and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L costs $32,000 and its expected cash flows would be $14,700 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend?

Select the correct answer.

I. Neither S or L, since each project's NPV < 0.

II. Project L, since the NPVL > NPVS.

III. Project S, since the NPVS > NPVL.

IV. Both Projects S and L, since both projects have IRR's > 0.

V. Both Projects S and L, since both projects have NPV's > 0.

Request for Solution File

Ask an Expert for Answer!!
Financial Management: Project s costs 11000 and its expected cash flows would be
Reference No:- TGS02858680

Expected delivery within 24 Hours