Project priority matrix for the conveyor belt project


Project Description:

o    New computer-controlled Conveyor Belt Project

o    The Conveyor Belt Project should move and position items on the conveyor within < 1 millimeter

o    This new project will produce new system for future installations and for replacement of those in the field, at a low cost

o    The computer-controlled conveyor belt has the potential to be a critical unit in 30% of the systems installed in factories

o    The new system is also easier to update with future technologies

The project Priority Matrix for the Conveyor Belt Project (CBP) is:


Time

Scope

Cost

Constrain

X

 

 

Enhance

 

X

 

Accept

 

 

X