Project manager paul is purchasing 100 laptops and 20


Project Manager Paul is purchasing 100 laptops and 20 desktop computers for her project, and the delivery of the computers is time-critical. Billie Jo would like to provide an incentive to the seller for the timely delivery of the computers. Paul, along with the buyer on the project team, has agreed that the selected seller will be paid the cost of the computers plus a 10% fee. Which contract type is being used in this case? "

A. Cost plus a percentage of cost contract

B. T&M with incentive

C. Cost plus a fixed fee

D. Fixed Cost.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Project manager paul is purchasing 100 laptops and 20
Reference No:- TGS01508777

Expected delivery within 24 Hours