Project l costs 35000 its expected cash inflows are 12000


Payback period

Project L costs $35,000, its expected cash inflows are $12,000 per year for 11 years, and its WACC is 9%. What is the project's payback? Round your answer to two decimal places.

Request for Solution File

Ask an Expert for Answer!!
Financial Management: Project l costs 35000 its expected cash inflows are 12000