Project expected npv for appropriate cost of capital


Consider the given project data:

(1) A $500 feasibility study will be conducted at t = 0.

(2) If the study indicates potential, the firm will spend $1,000 at t = 1 to build a prototype. The best estimate now is that there is an 80 percent chance that the study will indicate potential, and a 20 percent chance that it will not.

(3) If reaction to the prototype is good, the firm will spend $10,000 to build a production plant at t = 2. The best estimate now is that there is a 60 percent chance that the reaction to the prototype will be good, and a 40 percent chance that it will be poor.

(4) If the plant is built, there is a 50 percent chance of a t = 3 cash inflow of $16,000 and a 50 percent chance of a $13,000 cash inflow.

If the appropriate cost of capital is 10 percent, what is the project's expected NPV?

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Project expected npv for appropriate cost of capital
Reference No:- TGS01988471

Now Priced at $25 (50% Discount)

Recommended (99%)

Rated (4.3/5)