Project crashing problem continuednbspwhat is the normal


PROJECT CRASHING PROBLEM (continued): What is the normal duration of the project?What is the total crashing cost to crash the project by 4 days?What is the critical path?What is the exact sequence of activities to crash, to reduce the project by 4 days?

Activity

Immediate Predecessor

Normal Time

(days)

Crash Time

(days)

Normal Cost

($)

Crash Cost

($)

A

-

5

4

1000

1400

B

-

3

3

800

-

C

A,B

3

1

600

900

D

B

4

2

1600

2000

E

C,D

5

3

800

1200

F

E

2

1

1300

1400