Project completion time and the critical path


Dave Fletcher (see Problem) was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times:

ACTIVITY        TIME   (WEEKS)      ACTIVITY TIME   (WEEKS)
A                      6            E                  4
B                      7            F                  6
C                      3            G                 10
D                      2            H                  7

Data from Problem

           IMMEDIATE                                        IMMEDIATE
ACTIVITY     PREDECESSOR,(S)           ACTIVITY      PREDECESSOR(S)
A                     -             E                       B
B                     -             F                        B
C                                   A                       G C, E
D                                   A                       H D, F

Solution Preview :

Prepared by a verified Expert
Other Management: Project completion time and the critical path
Reference No:- TGS01438756

Now Priced at $25 (50% Discount)

Recommended (94%)

Rated (4.6/5)