Production scheduling for optimized production technology


I) Which of the following is one of Dr. Eli Goldratt's rules of production scheduling for optimized production technology?

• An hour saved at a bottleneck operation does not increase the process flow.

• If you lose an hour at a bottleneck it is better than making scrap.

• Do not allow bottlenecks to govern the flow of the line.

• Utilization and activation of a resource are not the same.

II) Which is the one correct value stream principle?

• Look for efficiencies in the factory, office, physical, procedural, and technical operations.

• Eliminate waste that stops, slows down, or diverts the value stream.

• Concentrate on speeding up value-adding operations rather than removing waste.

• Keep the value stream moving at minimum velocity.