Production planner for scott sampson products


Problem: As the production planner for Scott Sampson Products, Inc., you have been given a bill of material for a bracket that is made up of a base, two springs, and four clamps. The base is assembled from one clamp and two housings. Each clamp has one handle and one casting. Each housing has two bearings and one shaft. There is no inventory on hand.

1) Design a product structure nothing the quantities for each item and show the low-level coding.

2) Determine the gross quantities needed of each item if you are to assemble 50 brackets.

3) Complete the net quantities needed if there are 25 of the base and 100 of the clamp in stock.

Solution Preview :

Prepared by a verified Expert
Other Management: Production planner for scott sampson products
Reference No:- TGS02012065

Now Priced at $25 (50% Discount)

Recommended (93%)

Rated (4.5/5)