Production of soft drinks


The production manager for the Softy soft drink company is considering the production of 2 kinds of soft drinks: regular and diet. Two of her resources are production time (8 hours = 480 minutes per day) and syrup (1 of the ingredients) limited to 675 gallons per day. To produce a regular case requires 2 minutes and 5 gallons of syrup, while a diet case needs 4 minutes and 3 gallons of syrup. Profits for regular soft drink are $3.00 per case and profits for diet soft drink are $2.00 per case. What is the time constraint?

Answer

2R + 4D = 480

2D + 4R = 480

2R + 3D = 480

3R + 2D = 480