Processing sequence


An automobile detailing shop has the following jobs waiting to be processed. All jobs (cars requiring detailing) must first be cleaned, then waxed.

Job C1 C2 C3 C4 C5

Cleaning Time 9 6 5 3 8

Waxing Time 6 2 7 5 4

a. What processing sequence will minimize the makespan for these jobs?

b. What is the minimum makespan for this set of five jobs?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Processing sequence
Reference No:- TGS057436

Expected delivery within 24 Hours