Process as unit-level-batch-level and product-level


Problem:

Funk Manufacturing Company produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. Costs have been assigned to each activity using direct tracing and resource drivers:

Engineering    $125,000
Setups             112,500
Machining        250,000
Inspection       100,000

Activity drivers for each activity have been identified and their practical capacities listed:

Machine hours           50,000
Setups                          400
Engineering hours      10,000
Inspection hours          5,000
Required:

Q1. Identify the activities within each process as unit-level, batch-level, product-level, or facility-level.

Q2. Prepare a summary of cost/activity data using the following format:

Overhead Total Cost Activity Estimated Cost per
Activity of Activity Driver Driver Level Driver

c.  Compute the activity rates for each process.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Process as unit-level-batch-level and product-level
Reference No:- TGS01904989

Now Priced at $20 (50% Discount)

Recommended (97%)

Rated (4.9/5)