Problem 1nbsp the manger of a crew that installs carpets


Problem 1:  The manger of a crew that installs carpets has tracked the crew's output over the past several weeks, and the data are as follows:

Week

Crew Size

Yards Installed

1

4

480

2

3

351

3

4

484

4

2

250

5

3

348

6

2

250

Calculate labor productivity and multifactor productivity for each of the weeks. What can you infer about the relationship between crew size and productivity?

Problem 2:

Time Period

Demand

6 years ago

28

5 years ago

21

4 years ago

42

3 years ago

35

2 years ago

56

Last year

49

Required:

a. What is this year's forecast using a six-year moving average?

b. What is this year's forecast using a three year weighted moving average, where the weights are .5, .33, .17?

Request for Solution File

Ask an Expert for Answer!!
Business Management: Problem 1nbsp the manger of a crew that installs carpets
Reference No:- TGS01288716

Expected delivery within 24 Hours