Probability of completing all activities


Assignment:

The project of building a backyard swimming pool consists of eight major activities and has to be completed within 19 weeks. The activities and related data are given in the following table:

Activity

Immediate predecessor

Activity time (weeks)

A

-

3

B

-

6

C

A

2

D

B,C

5

E

D

4

F

E

3

G

B,C

9

H

F,G

3

a.  Draw a network diagram for this problem.

b. Determine the critical path and the expected project completion time.

c.  Assume the project variance is 4 weeks2.

i.  What is the probability that all the activities are completed within 19 weeks?

ii.  When is the due date if there is a 90% of completing all the activities?

Provide complete and step by step solution for the question and show calculations and use formulas.

Solution Preview :

Prepared by a verified Expert
Basic Statistics: Probability of completing all activities
Reference No:- TGS01935950