Preparing a flexible budget performance report


Problem: TipTop Flight School offers flying lessons at a small municipal airport. The school's owner and manager has been attempting to evaluate performance and control costs using a variance report that compares the planning budget to actual results. A recent variance report appears below:

TipTop Flight School
Variance Report
For the Month Ended July 31
Planning Actual
Budget Results Variances
Lessons . . . . . . . . . . . . . . . . . . 150 155
Revenue . . . . . . . . . . . . . . . . . $33,000 $33,900 $900 F
Expenses:
Instructor wages . . . . . . . . . 9,750 9,870 120 U
Aircraft depreciation . . . . . . 5,700 5,890 190 U
Fuel . . . . . . . . . . . . . . . . . . . 2,250 2,750 500 U
Maintenance . . . . . . . . . . . . 2,330 2,450 120 U
Ground facility expenses . . . 1,550 1,540 10 F
Administration . . . . . . . . . . . 3,390 3,320 70 F
Total expense . . . . . . . . . . . . . 24,970 25,820 850 U
Net operating income . . . . . . . $ 8,030 $ 8,080 $ 50 F

After several months of using such variance reports, the owner has become frustrated. For example, she is quite confi dent that instructor wages were very tightly controlled in July, but the report shows an unfavorable variance.

The planning budget was developed using the following formulas, where q is the number of lessons sold:

Cost Formulas
Revenue . . . . . . . . . . . . . . .....................$220q
Instructor wages . . . . . . . . . . . . . . . . . . . $65q
Aircraft depreciation . . . . . . . . . . . . . . . . $38q
Fuel . . . . . . . . . . . . . . . . . . . . . . . . . . . . $15q
Maintenance . . . . . . . . . . . . . . . . . . . . . . $530 $12q
Ground facility expenses . . . . . . . . . . . . $1,250 $2q
Administration . . . . . . . . . . . . . . . . . . . . . $3,240 $1q

Required:

1. Should the owner feel frustrated with the variance reports? Explain.

2. Prepare a flexible budget performance report for the school for July.

3. Evaluate the school's performance for July.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Preparing a flexible budget performance report
Reference No:- TGS01909425

Now Priced at $25 (50% Discount)

Recommended (93%)

Rated (4.5/5)