Question - Production Budget and Direct Labor Cost Budgets

Two-Leg Company manufactures slacks and jeans under a variety of brand names, such as Kickers and 101 Denims. Slacks and jeans are assembled by a variety of different sewing operations. Assume that the sales budget for Kickers and 101 Denims shows estimated sales of 21,610 and 38,720 pairs, respectively, for March 2012. The finished goods inventory is assumed as follows:


Kickers

101 Denims

March 1 estimated inventory

970

1,090

March 31 desired inventory

360

1,370

Assume the following direct labor data per 10 pairs of Kickers and 101 Denims for four different sewing operations:


Direct Labor per 10 Pairs


Kickers

101 Denims

Inseam

21 minutes

14 minutes

Outerseam

25

17

Pockets

8

10

Zipper

12

7

Total

66 minutes

48 minutes

a. Prepare a production budget for March.

b. Prepare the March direct labor cost budget for the four sewing operations, assuming a $13.00 wage per hour for the inseam and outerseam sewing operations and a $18.00 wage per hour for the pocket and zipper sewing operations.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Prepare the march direct labor cost budget for the four
Reference No:- TGS02613239

Now Priced at $25 (50% Discount)

Recommended (97%)

Rated (4.9/5)