Prepare mrp schedule for items to cover six-week planning


A product has this indented bill of materials:
Level
0 1 2 3 Quantity per parent
X285 1
A10 3
T3 1
Z7 2
V1 2
J20 2
H8 1
U4 2
M30 3
P2 2
V1 1

This inventory status report has just been issued for the project:
Item Code On Hand Safety Stock Allocated Lot Size Lead Time (weeks)
X285 250 50 0 LFL 1
A10 900 100 0 LFL 1
J20 850 100 10 LFL 1
M30 1100 100 35 LFL 1
T3 750 300 60 LFL 1
V1 2000 500 110 2000+ 1
H8 500 300 90 750+ 2
U4 500 300 0 1000+ 1
P2 1000 300 105 500+ 1
Z7 2500 500 250 2000 2

Prepare an MRP schedule for all the items to cover a six-week planning horizon if the MPS for product X285 shows an estimated demand or grass requirement of 80, 135, 280, 155, 210, and 275, in weeks 1 through 6, respectively.