Prepare cost sheet showing production and set-up costs


Question:

A component item involves material cost of Rs. 6 per unit and 10 minutes to produce. The operator is paid Rs. 72 per hour and machine hour rate is Rs. 150. The setting-up of the machine to produce the component takes 2 hours and 20 minutes. Prepare cost sheet showing production and set-up costs for a batch of (1) 100 units and (b) 1000 units

Request for Solution File

Ask an Expert for Answer!!
Cost Accounting: Prepare cost sheet showing production and set-up costs
Reference No:- TGS02041851

Expected delivery within 24 Hours