Prepare an earned value management report


Assignment:

Prepare and essay to answer the following questions:

A project is about a third of the way through its scheduled activities and an earned value management report has been prepared. The summary indicates that it has a CPI of 0.9 and an SPI of 0.8. What do these two values tell you about the project?

A project is about half done with a CV of $(4,000) due to a typical costs in the first half of the project. Its project manager provides an ETC of $50,000. Interpret this statement in your own words.