Prepare a simple budget showing an order of magnitude


Prepare a simple budget showing an order of magnitude estimate, a budget estimate, and a definitive estimate. What did you have to do to bring each successive budget closer to the final working budget?

The project network diagram has been constructed, and the project completion date is beyond the management-imposed deadline. You have compressed the schedule as much as possible by introducing parallel work through changes from FS to SS dependencies, and you still do not meet the schedule deadline. What would you do?

 

 

Solution Preview :

Prepared by a verified Expert
Management Theories: Prepare a simple budget showing an order of magnitude
Reference No:- TGS0908632

Now Priced at $30 (50% Discount)

Recommended (90%)

Rated (4.3/5)