Prepare a schedule of cost of goods manufactured


Problem: Schedules of Cost of Goods Manufactured and Cost of Goods Sold; Income Statement

The following data from the just completed year are taken from the accounting records of Eccles Company:

Sales ......................................................................................... $643,000
Direct labor cost ........................................................................... $90,000
Raw material purchases .............................................................. $132,000
Selling expenses ......................................................................... $100,000
Administrative expenses ............................................................... $43,000
Manufacturing overhead applied to work in process.......................  $210,000
Actual manufacturing overhead costs ..........................................  $220,000
Inventories:
Beginning of
Year
End of Year
Raw materials ............................................... $8,000 $10,000
Work in process ............................................ $5,000 $20,000
Finished goods ............................................. $70,000 $25,000

Ending raw material inventory = $8,000;
Ending work in process inventory = $16,000

Required:

1. Prepare a schedule of cost of goods manufactured. Assume all raw materials used in production were direct materials.

2. Prepare a schedule of cost of goods sold.

3. Prepare an income statement.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Prepare a schedule of cost of goods manufactured
Reference No:- TGS01905013

Now Priced at $25 (50% Discount)

Recommended (91%)

Rated (4.3/5)