Prepare a production plan for company flower design


Flower design

The general manager of the flower design company asked you to develop a production plan for your new line of perfume. You must calculate the total cost of that plan. The following is the data you need to develop the plan:

Spring -11,000

Summer-7,000

Fall -9,000

Winter-10,000

• Winter at the beginning of spring is 6,000 units

• At the beginning of spring there are 25 employees

• It is expected to hire temporary employees early fall and dismiss them at the end of autumn

• The spring and fall seasons are a lot of work, so management allows overtime to be applied only if necessary in order to avoid stock outs. Overtime is not allowed in summer or winter.

• According to staff, equipment and facilities, among other elements, it was determined that 0.25 units per hour of work could be produced, with eight hours per day and 60 days per season.

Recruitment- $ 125 per employee

Dismissal- $ 180 per employee

Inventory- $ 3 per unit / season

Backorder $ 8 per unit

Straight time $ 8.10 per hour

Assignment -

1. Prepare a production plan for company flower design

2. Calculate the total cost of the proposed plan

3. Present plan in table form in Excel