Prepare a material requirements plan for component d d can


Eighty units of end item X are needed at the beginning of week 6, and another 10 units are needed at the beginning of week 8. Prepare a material requirements plan for component D. D can only be ordered in whole cases. One case of D is automatically received every other week, beginning in week 1 (i.e., weeks 1, 3, 5, 7). Lot-for-lot ordering will be used for all items except D. Also, there are 20 units of B and 15 units of D now on hand. Lead times for all items are a function of quantity: one week for up to 100 units, two weeks for 101 to 200 units, three weeks for 201 to 300 units, and four weeks for 301 or more units.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Prepare a material requirements plan for component d d can
Reference No:- TGS02910357

Expected delivery within 24 Hours