Prepare a material requirements plan for component d d can


Eighty units of end item X are needed at the beginning of week 6, and another 30 units are needed at the beginning of week 8.

Picture

Prepare a material requirements plan for component D. D can only be ordered in whole cases (50 units per case). One case of D is automatically received every other week, beginning in week 1 (i.e., weeks 1, 3, 5, 7). Also, there are 30 units of B and 20 units of D now on hand. Lead times for all items are a function of quantity: one week for up to 100 units, two weeks for 101 to 200 units, three weeks for 201 to 300 units, and four weeks for 301 or more units. (Leave no cells blank - be certain to enter "0" wherever required.)

Part D Beg. Inv. 1 2 3 4 5 6 7 8
Gross requirements








Scheduled receipts








On hand








Net requirements








Planned-order receipt








Planned-order release









Request for Solution File

Ask an Expert for Answer!!
Management Theories: Prepare a material requirements plan for component d d can
Reference No:- TGS01484895

Expected delivery within 24 Hours