Prepare a forecast for september assuming actual september


A dry cleaner uses exponential smoothing to forecast equipment usage at its main plant. August usage was forecasted to be 50 percent of capacity; actual usage was 52 percent of capacity. A smoothing constant of .10 is used.

a. Prepare a forecast for September. (Round your final answer to 2 decimal places.)

Forecast for September             percent of capacity

b. Assuming actual September usage of 57 percent, prepare a forecast for October usage. (Round your answer to 2 decimal places.)

Forecast for October             percent of capacity