At the beginning of 19x4, Beal Company adopted the following standards:

Direct material (3 pounds @ $2.50 per pound)

$ 7.50

Direct labor (5 hours 0 $7.50 per hour)

37.50

Factory overhead:


Variable ($3.00 per direct labor hour)

15.00

Fixed ($4.00 per direct labor hour)

20.00

Standard cost per unit

$80.00

Normal volume per month is 40,000 direct labor hours. Beal's January 19x4 budget was based on normal volume. During January, Beal produced 7,800 units, with records indicating the following:

Direct material purchased

25,000 pounds @ $2.60

Direct material used

23,100 pounds

Direct labor

40,100hours @ $7.30

Factory overhead

$300,000

(a)Prepare a flexible budget for January 19x4 production costs, based on actual production of 7,800 units.

(b)For the month of January 19x4, compute the following variances, indicating whether each is favorable or unfavorable:

1. Direct materials price variance, based on purchases

2. Direct materials usage variance

3. Direct labor rate variance

4. Direct labor efficiency variance

5. Factory overhead spending variance

6. Variable factory overhead efficiency variance

7. Factory overhead volume variance

(CPA, adapted)

Solution Preview :

Prepared by a verified Expert
Financial Accounting: Prepare a flexible budget for january 19x4 production costs
Reference No:- TGS0781560

Now Priced at $30 (50% Discount)

Recommended (98%)

Rated (4.3/5)