Prepare a direct labor budget by quarters


For Mize Company, units to be produced are 5,580 in quarter 1 and 6,430 in quarter 2. It takes 1.5 hours to make a finished unit, and the expected hourly wage rate is $16 per hour. Prepare a direct labor budget by quarters for the 6 months ending June 30, 2012