Prepare a daily assignment sheet for personnel with the goal


Assignment: Project Management Logical Question

A project has 11 activities that can be accomplished either by one person working alone or by several people working together. The activities, precedence constraints, and time estimates are given in Table below. Suppose that you have up to five people who can be assigned on any given day. A person must work full days on each activity, but the number of people working on an activity can vary from day to day.

A. Prepare an AOA network diagram, and calculate the critical path, total slacks, and free slacks assuming that one person (independently) is working on each task.

B. Prepare an early-start Gantt chart.

C. Prepare a daily assignment sheet for personnel with the goal of finishing the project in the minimum amount of time.

D. Prepare a daily assignment sheet to "best" balance the workforce assigned to the project.

E. By how many days could the project be compressed if unlimited personnel resources were available?

Format your assignment according to the give formatting requirements:

1. The answer must be double spaced, typed, using Times New Roman font (size 12), with one-inch margins on all sides.

2. The response also includes a cover page containing the title of the assignment, the course title, the student's name, and the date. The cover page is not included in the required page length.

3. Also include a reference page. The references and Citations should follow APA format. The reference page is not included in the required page length.

Request for Solution File

Ask an Expert for Answer!!
Project Management: Prepare a daily assignment sheet for personnel with the goal
Reference No:- TGS03060527

Expected delivery within 24 Hours