Willis expected its annual overhead costs to be $300,000 and direct labor costs to be $500,000. Actual overhead was $290,000, and actual labor costs totaled $550,000. How much is the company's predetermined overhead rate to the nearest cent?

a. $0.58

b. $0.53

c. $0.55

d. $0.60