A money manager is holding the following portfolio:

Stock Amount Invested Beta
1 $300,000 0.6
2 300,000 1.0
3 500,000 1.4
4 500,000 1.8

The risk-free rate is 6 percent and the portfolio's required rate of return is 12.5 percent. The manager would like to sell all of her holdings of Stock 1 and use the proceeds to purchase more shares of Stock 4. What would be the portfolio's required rate of return following this change?

Solution Preview :

Prepared by a verified Expert
Finance Basics: Portfolio required rate of return following the change
Reference No:- TGS02047497