Policy variable representing the safety stock percentage


A company using a Kanban system has an inefficient machine group. For example, the daily demand for part L105A is 3,000 units. The average waiting time for a container of parts is 0.8 day. The processing time for a container of L105A is 0.2 day, and a container holds 270 units. Currently, there are 20 containers for this item?

a. What is the value of the policy variable representing the safety stock percentage?

b. What is the total planned inventory (work in process and finished goods) for item L105A?

c. Suppose the safety stock percentage was 0 (zero). How many containers would be needed now? What is the effect of the safety stock percentage in this example?