Pointy-haired boss or just boss


Task: A 12 month project is estimated to spend one million dollars over the life of the project. At Month 3, the following numbers have been recorded:

Month   PV        EV         AC
1       $10K      $1K        $5K
2       $25K      $3K       $15K
3       $75K      $6K       $40K

Question 1. When will it finish? Crude approximation. Show all calculations.

Question 2. What will it cost? Show all calculations.

Question 3. What would you do as the PHB (Pointy-Haired Boss or just Boss)? State all reasons here.

PLEASE SHOW ALL STEPS AND CALCULATIONS.

Solution Preview :

Prepared by a verified Expert
Microeconomics: Pointy-haired boss or just boss
Reference No:- TGS01745548

Now Priced at $25 (50% Discount)

Recommended (96%)

Rated (4.8/5)