Pinnacle corp budgeted 700000 of overhead cost for the


Pinnacle Corp. budgeted $700,000 of overhead cost for the current year. Actual overhead costs for the year were $650,000. Pinnacle’s plant wide allocation base, machine hours, was budgeted at 100,000 hours. Actual machine hours were 80,000. A total of 100,000 units was budgeted to be produced and 98,000 units were actually produced. Pinnacle’s plant wide factory overhead rate for the current year is:

a. $8.13 per machine hour

b. $7.00 per machine hour

c.  $6.50 per machine hour

 

d. $8.75 per machine hour

Request for Solution File

Ask an Expert for Answer!!
Financial Accounting: Pinnacle corp budgeted 700000 of overhead cost for the
Reference No:- TGS01270019

Expected delivery within 24 Hours