Phil construction inc had a 3-year project whose contract


PHIL Construction, Inc. had a 3-year project whose contract price was $8,000,000. Construction activities are summarized in the table below.


12/31/14

12/31/15

12/31/16

Costs to date

2,000,000

5,000,000

6,000,000

Additional costs to complete

3,000,000

1,000,000

-0-

Progress billings to date

2,500,000

5,500,000

8,000,000

Cash collected to date

2,300,000

5,400,000

8,000,000

Instructions: Prepare any necessary journal entries for the above project in 2014, 2015 & 2016 using 1) the percentage of completion method, 2) the completed contract method.

Thank you very much in advance.

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Phil construction inc had a 3-year project whose contract
Reference No:- TGS02608227

Expected delivery within 24 Hours