You have been asked to create a project plan to build a playground for children in your local community. Your project should have 10-15 tasks (therefore, your network will have 10-15 nodes). Please include the following:

Develop a WBS for your project. Hand-draw a network diagram for your project. Perform the forward and backward pass to calculate the slack for each task. Write a short narrative that describes your network’s overall sensitivity.