Perform production tests of completed pump station


Discussion:

Q: The Midwest Gas Transmission Company must build a pump station on one of its major pipelines. The activities involved in completing this project are given in the following table.

Activity Description Precedence

A Carry out project administration none

B Hire pipeline construction personnel A

C Purchase pump station equipment A

D Transport pump station equipment to pipeline location C

E Run simulation of pump station operation A

F Inspect equipment C, B

G Construct pump station B, D

H Perform production tests of completed pump station E

I Start up pump station F, G

J Carry out performance evaluation I

K Complete accounting data H, J

Construct an Activity on the Arrow (AOA) network for this project.