Perform a financial analysis for a project assume the


Perform a financial analysis for a project. Assume the projected costs and benefits for the project are spread over five years as follows: Estimated costs are $300,000 in year 1 and $50,000 in years 2-5.Estimated benefits are $100,000 in year 1 and $200,000 in years 2-5. Discount rate is 10% and round the discount factors to two decimal points. What is the NPV of the project?