Perform a financial analysis for a project assume the


Perform a financial analysis for a project. Assume the projected costs and benefits for this project are spread over four years as follows: Estimated costs are $200,000 in year 1 and $30,000 each year in years 2, 3, and 4. Estimated benefits are $0 in year 1 and $100,000 each year in years 2, 3, and 4. Use a 9 percent discount rate and round the discount factors to two decimal places. Create a spreadsheet to calculate and clearly display the NPV, ROI, and year in which payback occurs. In addition, write a paragraph explaining whether you would recommend investing in this project, based on your financial