Percentage-of-completion method for revenue recognition


Problem: Jacks Contractors received a contract to construct a mental health facility for $2,500,000.

Construction was begun in 2005 and completed in 2006. Cost and other data are presented below:

                                                                 2005            2006
Costs incurred during the year                $1,500,000    $1,300,000
Remaining estimated costs to complete      1,200,000           0
Billings during the year                             1,200,000     1,300,000
Cash collections during the year                1,000,000     1,500,000

Assume that Jacks uses the percentage-of-completion method for revenue recognition.

Compute the amount of gross profit recognized during 2005 and 2006.