Percentage of completion method


Questions:

Chicago contractors got  $5,400,000 contract to construct a school building for the City of Chicago. Work on this contract began in 2013 and the financial data pertaining to this contract is available here.

Cost incurred till Dec.31, 2013                      $1,080,000
Billings made to City                                    $1,000,000
Amount collected from City                           $ 750,000

The estimated future cost to complete this contract is $3,240,000.

(a) Prepare Chicago contractors 2013 journal entries using percentage of completion method.

(b) Show how the contract accounts will appear in the Balance Sheet of Chicago Contractors on 12/31/2013.