Overhead variances. Smolenski, Inc., uses standard costing. The company reported the following overhead information for the current period:

Actual Overhead Incurred

$13,600, of Which $3,500 Is Fixed

Budgeted  Fixed  Overhead

$3,300

Variable Overhead Rate per Machine Hour

$   3

Standard Hours Allowed for Actual Production

3,500

Actual Machine Hours Used

3,200

Calculate the variable and fixed overhead  variances.